BetaActiveSolarBatteryNVELBNL
200 MW hybrid in Clark, NV · In queue since September 2020 · Proposed COD June 2024
200 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 9m
Schedule
21 months past proposed COD
Construction75%
Queue EntrySep 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-06-30
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.