BetaActiveBatteryNVELBNL
30 MW storage in Clark, NV · In queue since September 2019 · Proposed COD September 2023
30 MW
Capacity
1
Components
Battery
6y 6m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4 years
Schedule
31 months past proposed COD
Construction75%
Queue EntrySep 26, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2023-09-01
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL
No news available for this project.