BetaSuspendedSolarBatteryNVELBNL
350 MW hybrid in Clark, NV · In queue since November 2018 · Proposed COD September 2024
350 MW
Capacity
1
Components
Solar
7y 4m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
5y 10m
Suspended38%
Queue EntryNov 30, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
NV Energy
Entity
NVE
Data Source
LBNL