— Project Summary

Queue ID
N-C-NC5-009
Capacity
300 MW
Technology
Wind
Status
active
Location
Mohave, AZ
Region
West
Developer
IA Status

BetaActiveWindN-CLBNL

300 MW generation in Mohave, AZ · In queue since April 2022 · Proposed COD September 2027

300 MW

Capacity

1

Components

Wind

3y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 5m

Pre-Study0%
Queue EntryApr 5, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

AZ

County

Mohave

Region

West

Developer

Utility

Navajo-Crystal

Entity

N-C

Point of Interconnection

Navajo-Crystal 525 kV Line

Data Source

LBNL

No news available for this project.