200 MW hybrid in Clark, NV · In queue since May 2018 · Proposed COD September 2021
200 MW
Capacity
1
Components
Solar
7y 10m
In Queue
—
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
3y 4m
Schedule
56 months past proposed COD
Pre-Study0%
Queue EntryMay 2, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-09-01
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Navajo-Crystal
Entity
N-C
Point of Interconnection
South Crystal 525 kV Switchyard
Data Source
LBNL