— Project Summary

Queue ID
N-C-NC5-005
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
West
Developer
IA Status

BetaActiveSolarBatteryN-CLBNL

200 MW hybrid in Clark, NV · In queue since May 2018 · Proposed COD September 2021

200 MW

Capacity

1

Components

Solar

7y 10m

In Queue

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 4m

Schedule

56 months past proposed COD

Pre-Study0%
Queue EntryMay 2, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-09-01

Project Details

State

NV

County

Clark

Region

West

Developer

Utility

Navajo-Crystal

Entity

N-C

Point of Interconnection

South Crystal 525 kV Switchyard

Data Source

LBNL

No news available for this project.