— Project Summary

Queue ID
N-C-NC5-002
Capacity
499 MW
Technology
Other
Status
active
Location
Clark, NV
Region
West
Developer
IA Status

BetaActiveOtherN-CLBNL

499 MW generation in Clark, NV · In queue since May 2017 · Proposed COD June 2022

499 MW

Capacity

1

Components

Other

8y 10m

In Queue

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

5y 1m

Schedule

46 months past proposed COD

Pre-Study0%
Queue EntryMay 26, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-06-14

Project Details

State

NV

County

Clark

Region

West

Developer

Utility

Navajo-Crystal

Entity

N-C

Point of Interconnection

South Crystal 525 kV Switchyard

Data Source

LBNL

No news available for this project.