499 MW generation in Clark, NV · In queue since May 2017 · Proposed COD June 2022
499 MW
Capacity
1
Components
Other
8y 10m
In Queue
—
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
5y 1m
Schedule
46 months past proposed COD
Pre-Study0%
Queue EntryMay 26, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-14
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Navajo-Crystal
Entity
N-C
Point of Interconnection
South Crystal 525 kV Switchyard
Data Source
LBNL