BetaActiveSolarBatteryN-CLBNL
480 MW hybrid in Kane, UT · In queue since May 2015 · Proposed COD October 2028
480 MW
Capacity
1
Components
Solar
10y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
13y 5m
Pre-Study0%
Queue EntryMay 11, 2015
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-31
Project Details
State
UT
County
Kane
Region
West
Developer
—
Utility
Navajo-Crystal
Entity
N-C
Point of Interconnection
Navajo-Crystal 525 kV Line
Data Source
LBNL