BetaActiveWindMPCLBNL
258.4 MW generation in Grand Forks, ND · In queue since September 2023 · Proposed COD March 2028
258.4 MW
Capacity
1
Components
Wind
2y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Pre-Study0%
Queue EntrySep 26, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
ND
County
Grand Forks
Region
MISO
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Point of Interconnection
Lerfald Substation
Data Source
LBNL