BetaActiveWindMPCLBNL
300 MW generation in Oliver, ND · In queue since April 2019 · Proposed COD December 2023
300 MW
Capacity
1
Components
Wind
6y 11m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 8m
Schedule
28 months past proposed COD
Facilities Study50%
Queue EntryApr 25, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
ND
County
Oliver
Region
MISO
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Point of Interconnection
Square Butte 230 kV Substation
Data Source
LBNL
No news available for this project.