BetaActiveWindMPCLBNL
250 MW generation in Eddy, ND · In queue since February 2019 · Proposed COD November 2023
250 MW
Capacity
1
Components
Wind
7y 1m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 9m
Schedule
28 months past proposed COD
Facilities Study50%
Queue EntryFeb 21, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-30
Project Details
State
ND
County
Eddy
Region
MISO
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Point of Interconnection
Center-Prairie 345 kV Line
Data Source
LBNL
No news available for this project.