BetaActiveSolarMPCLBNL
170 MW generation in Richland, ND · In queue since May 2018 · Proposed COD April 2027
170 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 11m
Construction75%
Queue EntryMay 4, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-13
Project Details
State
ND
County
Richland
Region
MISO
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Point of Interconnection
Frontier-Wahpeton 230 kV Line
Data Source
LBNL
No news available for this project.