— Project Summary

Queue ID
MISO-S1131
Capacity
200 MW
Technology
Battery
Status
active
Location
Perry, IL
Region
MISO
Developer
IA Status

BetaActiveBattery StorageMISOLive · MISO

200 MW storage in Perry, IL · In queue since November 2025

200 MW

Capacity

0

Components

4 months

In Queue

IA Status

Interconnection Timeline

Total Duration

4 months

Pre-Study0%
Queue EntryNov 11, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IL

County

Perry

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

7JORD - 7CMDR 345.0kV

Data Source

Live · MISO

No news available for this project.