— Project Summary

Queue ID
MISO-S1112
Capacity
130 MW
Technology
Battery
Status
active
Location
Pike, IN
Region
MISO
Developer
IA Status

BetaActiveBattery StorageMISOLive · MISO

130 MW storage in Pike, IN · In queue since August 2025

130 MW

Capacity

0

Components

7 months

In Queue

IA Status

Interconnection Timeline

Total Duration

7 months

Pre-Study0%
Queue EntryAug 11, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IN

County

Pike

Region

MISO

Developer

Utility

SOUTHERN INDIANA GAS & ELECTRIC COMPANY D/B/A CENTERPOINT ENERGY INDIANA SOUTH

Entity

MISO

Point of Interconnection

Cato 138/69kV (facilities above 100kV)

Data Source

Live · MISO

No news available for this project.