— Project Summary

Queue ID
MISO-S1111
Capacity
263 MW
Technology
Other
Status
active
Location
Adair, IA
Region
MISO
Developer
IA Status

BetaActiveHybridMISOLive · MISO

263 MW generation in Adair, IA · In queue since July 2025

263 MW

Capacity

0

Components

8 months

In Queue

IA Status

Interconnection Timeline

Total Duration

8 months

Pre-Study0%
Queue EntryJul 31, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IA

County

Adair

Region

MISO

Developer

Utility

MIDAMERICAN ENERGY CO.

Entity

MISO

Point of Interconnection

ORIENT

Data Source

Live · MISO

No news available for this project.