— Project Summary

Queue ID
MISO-S1110
Capacity
100 MW
Technology
Battery
Status
active
Location
Chisago, MN
Region
MISO
Developer
IA Status

BetaActiveBattery StorageMISOLive · MISO

100 MW storage in Chisago, MN · In queue since August 2025

100 MW

Capacity

0

Components

7 months

In Queue

IA Status

Interconnection Timeline

Total Duration

7 months

Pre-Study0%
Queue EntryAug 22, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MN

County

Chisago

Region

MISO

Developer

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Point of Interconnection

CHISAGO COUNTY

Data Source

Live · MISO

No news available for this project.