BetaActiveBattery StorageMISOLive · MISO
200 MW storage in Mississippi, AR · In queue since June 2025
200 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
9 months
Pre-Study0%
Queue EntryJun 18, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
AR
County
Mississippi
Region
MISO
Developer
—
Utility
ENTERGY ARKANSAS, LLC
Entity
MISO
Point of Interconnection
BLYTHEVILLE I-55 - AECC BLYTHEVILLE NORTH 161.0kV
Data Source
Live · MISO
No news available for this project.