BetaActiveSolarMISOLive · MISO
188 MW generation in Vermilion, IL · In queue since May 2025
188 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
10 months
Pre-Study0%
Queue EntryMay 23, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
IL
County
Vermilion
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
Tilton Switchyard
Data Source
Live · MISO
No news available for this project.