BetaActiveBattery StorageMISOLive · MISO
200 MW storage in Perry, IL · In queue since April 2025
200 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
11 months
Pre-Study0%
Queue EntryApr 22, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
IL
County
Perry
Region
MISO
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Point of Interconnection
7ASTER - 7CMDR 345.0kV
Data Source
Live · MISO
No news available for this project.