BetaActiveBattery StorageMISOLive · MISO
200 MW storage in Nobles, MN · In queue since January 2025
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 2m
Pre-Study0%
Queue EntryJan 14, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MN
County
Nobles
Region
MISO
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Point of Interconnection
NOBLES COUNTY
Data Source
Live · MISO
No news available for this project.