— Project Summary

Queue ID
MISO-S1073
Capacity
150 MW
Technology
Other
Status
active
Location
Webster
Region
MISO
Developer
IA Status

BetaActiveMISOLive · MISO

150 MW generation in Webster · In queue since February 2025

150 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 1m

Pre-Study0%
Queue EntryFeb 19, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

County

Webster

Region

MISO

Developer

Utility

BIG RIVERS ELECTRIC CORPORATION

Entity

MISO

Point of Interconnection

Hopkins to Reid EVH 161kV

Data Source

Live · MISO

No news available for this project.