Surplus; J1658 — Project Summary

Queue ID
MISO-S1068
Capacity
150 MW
Technology
Battery
Status
active
Location
Region
MISO
Developer
IA Status

Surplus; J1658

BetaActiveBatteryMISOLBNL + Live

150 MW storage in · In queue since October 2024

150 MW

Capacity

1

Components

Battery

1y 5m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 5m

Pre-Study0%
Queue EntryOct 9, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

County

Region

MISO

Developer

Utility

Entity

MISO

Data Source

LBNL + Live

No news available for this project.