Surplus; J1224/J1329
BetaActiveOtherBatteryMISOLBNL + Live
85.05 MW hybrid in Washtenaw, MI · In queue since October 2024 · Proposed COD September 2028
85.05 MW
Capacity
1
Components
Other
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryOct 7, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
MI
County
Washtenaw
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
Majestic 345kV to Milan 345kV
Data Source
LBNL + Live
No news available for this project.