Surplus; J199/J202
BetaActiveOtherBatteryMISOLBNL + Live
100.3 MW hybrid in Tuscola, MI · In queue since July 2024 · Proposed COD January 2027
100.3 MW
Capacity
1
Components
Other
1y 8m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 6m
Pre-Study0%
Queue EntryJul 26, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-30
Project Details
State
MI
County
Tuscola
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
Dixon 120kV - Bus # 265182
Data Source
LBNL + Live
No news available for this project.