Queue ID
MISO-S1054
Capacity
550 MW
Technology
Wind
Status
active
Location
Cottonwood, MN
Region
MISO
Developer
IA Status

Surplus; Big Bend

BetaActiveWindOtherMISOLBNL + Live

550 MW hybrid in Cottonwood, MN · In queue since July 2024 · Proposed COD October 2027

550 MW

Capacity

1

Components

Wind

1y 8m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 3m

Pre-Study0%
Queue EntryJul 19, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-30

Project Details

State

MN

County

Cottonwood

Region

MISO

Developer

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Point of Interconnection

Lakefield Junction 345kV

Data Source

LBNL + Live