Surplus; J385
BetaActiveOtherBatteryMISOLBNL + Live
100 MW hybrid in Chisago, MN · In queue since July 2024 · Proposed COD October 2026
100 MW
Capacity
1
Components
Other
1y 8m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 3m
Pre-Study0%
Queue EntryJul 9, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
MN
County
Chisago
Region
MISO
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Point of Interconnection
Chisago County Substation
Data Source
LBNL + Live
No news available for this project.