Surplus; Shelby
BetaActiveSolarOtherMISOLBNL + Live
150 MW hybrid in Cumberland, IL · In queue since June 2024 · Proposed COD September 2026
150 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 3m
Pre-Study0%
Queue EntryJun 14, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-22
Project Details
State
IL
County
Cumberland
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
Neoga South 138kV
Data Source
LBNL + Live
No news available for this project.