Surplus; J442 — Project Summary

Queue ID
MISO-S1047
Capacity
120 MW
Technology
Battery
Status
active
Location
Codington, SD
Region
MISO
Developer
IA Status

Surplus; J442

BetaActiveOtherBatteryMISOLBNL + Live

120 MW hybrid in Codington, SD · In queue since October 2023 · Proposed COD November 2026

120 MW

Capacity

1

Components

Other

2y 5m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 1m

Pre-Study0%
Queue EntryOct 13, 2023

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-01

Project Details

State

SD

County

Codington

Region

MISO

Developer

Utility

OTTER TAIL POWER COMPANY

Entity

MISO

Point of Interconnection

Big Stone South 230kV

Data Source

LBNL + Live

No news available for this project.