Surplus; J1304
BetaActiveOtherBatteryMISOLBNL + Live
33 MW hybrid in Rock, WI · In queue since August 2022 · Proposed COD July 2023
33 MW
Capacity
1
Components
Other
3y 7m
In Queue
—
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
11 months
Schedule
33 months past proposed COD
Pre-Study0%
Queue EntryAug 15, 2022
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-07-01
Project Details
State
WI
County
Rock
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Townline Rd. - Paddock 138kV
Data Source
LBNL + Live
No news available for this project.