Surplus; J728
BetaActiveSolarOtherMISOLBNL + Live
90 MW hybrid in Isabella, MI · In queue since August 2022 · Proposed COD July 2025
90 MW
Capacity
1
Components
Solar
3y 7m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
8 months past proposed COD
Pre-Study0%
Queue EntryAug 19, 2022
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-30
Project Details
State
MI
County
Isabella
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
Salt River Substation 138kV
Data Source
LBNL + Live
No news available for this project.