Surplus; J717 — Project Summary

Queue ID
MISO-S1031
Capacity
90 MW
Technology
Solar
Status
active
Location
Isabella, MI
Region
MISO
Developer
IA Status

Surplus; J717

BetaActiveSolarOtherMISOLBNL + Live

90 MW hybrid in Isabella, MI · In queue since August 2022 · Proposed COD July 2025

90 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 11m

Schedule

8 months past proposed COD

Pre-Study0%
Queue EntryAug 19, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-30

Project Details

State

MI

County

Isabella

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

Salt River Substation 138kV

Data Source

LBNL + Live