Surplus; J1369
50 MW hybrid in Dubois, IN · In queue since May 2022 · Proposed COD July 2022
50 MW
Capacity
1
Components
Other
3y 10m
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
5 months
Total Duration
5 months
Schedule
45 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2022-07-01
State
IN
County
Dubois
Region
MISO
Developer
—
Utility
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Entity
MISO
Point of Interconnection
Dubois - Culley 138kV line
Data Source
LBNL + Live