Surplus; J1002 — Project Summary

Queue ID
MISO-S1024
Capacity
50 MW
Technology
Battery
Status
active
Location
Waushara, WI
Region
MISO
Developer
IA Status

Surplus; J1002

BetaActiveOtherBatteryMISOLBNL + Live

50 MW hybrid in Waushara, WI · In queue since May 2022 · Proposed COD January 2023

50 MW

Capacity

1

Components

Other

3y 10m

In Queue

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

8 months

Schedule

39 months past proposed COD

Pre-Study0%
Queue EntryMay 16, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-01-26

Project Details

State

WI

County

Waushara

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Wautoma 138kV

Data Source

LBNL + Live

No news available for this project.