Surplus; J1000 — Project Summary

Queue ID
MISO-S1023
Capacity
25 MW
Technology
Battery
Status
active
Location
Grant, WI
Region
MISO
Developer
IA Status

Surplus; J1000

BetaActiveOtherBatteryMISOLBNL + Live

25 MW hybrid in Grant, WI · In queue since May 2022 · Proposed COD March 2023

25 MW

Capacity

1

Components

Other

3y 10m

In Queue

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

10 months

Schedule

37 months past proposed COD

Pre-Study0%
Queue EntryMay 16, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-03-27

Project Details

State

WI

County

Grant

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Nelson Dewey - Lancaster 138kV

Data Source

LBNL + Live

No news available for this project.