Surplus; J1000
BetaActiveOtherBatteryMISOLBNL + Live
25 MW hybrid in Grant, WI · In queue since May 2022 · Proposed COD March 2023
25 MW
Capacity
1
Components
Other
3y 10m
In Queue
—
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
10 months
Schedule
37 months past proposed COD
Pre-Study0%
Queue EntryMay 16, 2022
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-03-27
Project Details
State
WI
County
Grant
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Nelson Dewey - Lancaster 138kV
Data Source
LBNL + Live