Surplus; J928
BetaActiveSolarOtherMISOLBNL + Live
55 MW hybrid in — · In queue since April 2022 · Proposed COD November 2025
55 MW
Capacity
1
Components
Solar
3y 11m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 7m
Schedule
5 months past proposed COD
Pre-Study0%
Queue EntryApr 11, 2022
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-01
Project Details
State
—
County
—
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Garden Corners 138kV
Data Source
LBNL + Live
No news available for this project.