Surplus; J928 — Project Summary

Queue ID
MISO-S1015
Capacity
55 MW
Technology
Solar
Status
active
Location
Region
MISO
Developer
IA Status

Surplus; J928

BetaActiveSolarOtherMISOLBNL + Live

55 MW hybrid in · In queue since April 2022 · Proposed COD November 2025

55 MW

Capacity

1

Components

Solar

3y 11m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

5 months past proposed COD

Pre-Study0%
Queue EntryApr 11, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-01

Project Details

State

County

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Garden Corners 138kV

Data Source

LBNL + Live

No news available for this project.