Surplus; J893 — Project Summary

Queue ID
MISO-S1000
Capacity
10 MW
Technology
Battery
Status
active
Location
Region
MISO
Developer
IA Status

Surplus; J893

BetaActiveOtherBatteryMISOLBNL + Live

10 MW hybrid in · In queue since June 2020

10 MW

Capacity

1

Components

Other

5y 9m

In Queue

IA Status

Interconnection Timeline

Total Duration

5y 9m

Pre-Study0%
Queue EntryJun 20, 2020

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

County

Region

MISO

Developer

Utility

Entity

MISO

Data Source

LBNL + Live

No news available for this project.