— Project Summary

Queue ID
MISO-R5086
Capacity
593 MW
Technology
Battery
Status
active
Location
Pointe Coupee, LA
Region
MISO
Developer
IA Status

BetaActiveBattery StorageMISOLive · MISO

593 MW storage in Pointe Coupee, LA · In queue since October 2025

593 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 17, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

LA

County

Pointe Coupee

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Big Cajun II 500kV Substation

Data Source

Live · MISO

No news available for this project.