Replacing 615 MW Coal with 615 MW BESS; Campbell Units 1 & 2
BetaActiveOtherBatteryMISOLBNL + Live
615 MW hybrid in — · In queue since June 2024 · Proposed COD March 2028
615 MW
Capacity
1
Components
Other
1y 9m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryJun 24, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-31
Project Details
State
—
County
—
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
"18CAMPBELLW_x001D_, _x001C_18CAMPBELLB
Data Source
LBNL + Live
No news available for this project.