BetaActiveWindMISOLBNL
4.6 MW generation in MN · In queue since March 2016 · Proposed COD November 2016
4.6 MW
Capacity
1
Components
Wind
10 years
In Queue
IA Executed
IA Status
COD target: 2016
Interconnection Timeline
Total Duration
8 months
Schedule
114 months past proposed COD
Construction75%
Queue EntryMar 17, 2016
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2016-11-15
Project Details
State
MN
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
1.5 miles SW of Red Lake Falls, MN
Data Source
LBNL
No news available for this project.