— Project Summary

Queue ID
MISO-R101
Capacity
4.6 MW
Technology
Wind
Status
active
Location
MN
Region
MISO
Developer
IA Status
IA Executed

BetaActiveWindMISOLBNL

4.6 MW generation in MN · In queue since March 2016 · Proposed COD November 2016

4.6 MW

Capacity

1

Components

Wind

10 years

In Queue

IA Executed

IA Status

COD target: 2016

Interconnection Timeline

Total Duration

8 months

Schedule

114 months past proposed COD

Construction75%
Queue EntryMar 17, 2016

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2016-11-15

Project Details

State

MN

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

1.5 miles SW of Red Lake Falls, MN

Data Source

LBNL

No news available for this project.