BetaActiveUnknownMISOLBNL
— generation in MI · In queue since April 2005 · Proposed COD April 2005
—
Capacity
0
Components
20y 11m
In Queue
IA Executed
IA Status
COD target: 2005
Interconnection Timeline
Total Duration
<1 month
Schedule
255 months past proposed COD
Construction75%
Queue EntryApr 1, 2005
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2005-04-01
Project Details
State
MI
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Unknown
Data Source
LBNL
No news available for this project.