— Project Summary

Queue ID
MISO-L006
Capacity
Technology
Other
Status
active
Location
MI
Region
MISO
Developer
IA Status
IA Executed

BetaActiveUnknownMISOLBNL

generation in MI · In queue since September 2004 · Proposed COD June 2005

Capacity

0

Components

21y 6m

In Queue

IA Executed

IA Status

COD target: 2005

Interconnection Timeline

Total Duration

9 months

Schedule

253 months past proposed COD

Construction75%
Queue EntrySep 27, 2004

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2005-06-01

Project Details

State

MI

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Unknown

Data Source

LBNL

No news available for this project.