BetaActiveUnknownMISOLBNL
— generation in OH · In queue since July 2004 · Proposed COD April 2009
—
Capacity
0
Components
21y 8m
In Queue
IA Executed
IA Status
COD target: 2009
Interconnection Timeline
Total Duration
4y 9m
Schedule
207 months past proposed COD
Construction75%
Queue EntryJul 22, 2004
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2009-04-01
Project Details
State
OH
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Unknown
Data Source
LBNL
No news available for this project.