— Project Summary

Queue ID
MISO-J643
Capacity
175 MW
Technology
Solar
Status
active
Location
IN
Region
MISO
Developer
IA Status
IA Executed

BetaActiveSolarMISOLBNL

175 MW generation in IN · In queue since May 2016 · Proposed COD April 2019

175 MW

Capacity

1

Components

Solar

9y 10m

In Queue

IA Executed

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2y 11m

Schedule

85 months past proposed COD

Construction75%
Queue EntryMay 9, 2016

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2019-04-01

Project Details

State

IN

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Schahfer Tap (17 SCHAFR_TAP)138kv

Data Source

LBNL

No news available for this project.