BetaActiveSolarMISOLBNL
100 MW generation in MS · In queue since May 2016 · Proposed COD September 2018
100 MW
Capacity
1
Components
Solar
9y 10m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2y 4m
Schedule
92 months past proposed COD
Construction75%
Queue EntryMay 9, 2016
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2018-09-01
Project Details
State
MS
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Ruleville 115kV Sub
Data Source
LBNL
No news available for this project.