BetaActiveGasMISOLBNL
6.4 MW generation in MI · In queue since May 2016 · Proposed COD May 2018
6.4 MW
Capacity
1
Components
Gas
9y 10m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2 years
Schedule
95 months past proposed COD
Construction75%
Queue EntryMay 6, 2016
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2018-05-31
Project Details
State
MI
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Township of Comstock, County of Kalmazoo, Morrow 138kV
Data Source
LBNL
No news available for this project.