BetaActiveSolarMISOLBNL + Live
98 MW generation in LA · In queue since January 2016 · Proposed COD September 2018
98 MW
Capacity
1
Components
Solar
10y 2m
In Queue
IA Executed
IA Status
Signed Jun 2018
Interconnection Timeline
Queue → IA
2y 5m
IA → COD
3 months
Total Duration
2y 5m
Schedule
92 months past proposed COD
Construction75%
Queue EntryJan 11, 2016
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection AgreementJun 1, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2018-09-01
Project Details
State
LA
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Galion 115kV Substation
Data Source
LBNL + Live
No news available for this project.