BetaActiveGasMISOLBNL
65 MW generation in IA · In queue since November 2015 · Proposed COD March 2017
65 MW
Capacity
1
Components
Gas
10y 4m
In Queue
IA Executed
IA Status
COD target: 2017
Interconnection Timeline
Total Duration
1y 4m
Schedule
110 months past proposed COD
Construction75%
Queue EntryNov 16, 2015
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2017-03-01
Project Details
State
IA
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Existing ITC Midwest Marshalltown substation
Data Source
LBNL
No news available for this project.