— Project Summary

Queue ID
MISO-J514
Capacity
65 MW
Technology
Gas
Status
active
Location
IA
Region
MISO
Developer
IA Status
IA Executed

BetaActiveGasMISOLBNL

65 MW generation in IA · In queue since November 2015 · Proposed COD March 2017

65 MW

Capacity

1

Components

Gas

10y 4m

In Queue

IA Executed

IA Status

COD target: 2017

Interconnection Timeline

Total Duration

1y 4m

Schedule

110 months past proposed COD

Construction75%
Queue EntryNov 16, 2015

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2017-03-01

Project Details

State

IA

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Existing ITC Midwest Marshalltown substation

Data Source

LBNL

No news available for this project.