100 MW generation in TX · In queue since September 2015 · Proposed COD September 2017
100 MW
Capacity
1
Components
Solar
10y 6m
In Queue
IA Executed
IA Status
COD target: 2017
Interconnection Timeline
Total Duration
2 years
Schedule
104 months past proposed COD
Construction75%
Queue EntrySep 14, 2015
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2017-09-01
Project Details
State
TX
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Line tap at 138 kV line approximately 6,000 ft SW of Gordon Sub
Data Source
LBNL
No news available for this project.