BetaActiveWindMISOLBNL
246 MW generation in MO · In queue since September 2015 · Proposed COD July 2020
246 MW
Capacity
1
Components
Wind
10y 6m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
4y 10m
Schedule
70 months past proposed COD
Construction75%
Queue EntrySep 14, 2015
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2020-07-01
Project Details
State
MO
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Atchison County to Booneville 345 kV Line Tap
Data Source
LBNL