BetaActiveBatteryMISOLBNL
30 MW storage in MI · In queue since May 2015 · Proposed COD October 2016
30 MW
Capacity
1
Components
Battery
10y 10m
In Queue
IA Executed
IA Status
COD target: 2016
Interconnection Timeline
Total Duration
1y 5m
Schedule
115 months past proposed COD
Construction75%
Queue EntryMay 18, 2015
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2016-10-01
Project Details
State
MI
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Stein 345 kV Substation
Data Source
LBNL