BetaActiveWindMISOLive · MISO
350 MW generation in Huron, MI · In queue since June 2025
350 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
9 months
Pre-Study0%
Queue EntryJun 6, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MI
County
Huron
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
RAPSON - STEIN 345.0kV
Data Source
Live · MISO
No news available for this project.